Beyond the Calculation

Shahzad Sheikh is currently supporting a range of FortisBC pipeline and facility projects with RAM, including pipeline engineering assessments, pressure uprating, station and facility modifications, valve replacements, tie-ins, and other brownfield upgrades. 

On several projects, Shahzad serves as Lead Project Engineer, coordinating engineering through different stages of design, reviewing drawings and calculations, checking compliance with CSA Z662 and FortisBC requirements, resolving technical issues, and supporting construction, testing and commissioning. 

“What I like about this work is that every project is a little different,” he says. “Some involve relatively straightforward modifications, while others require a much deeper review of the existing facility, historical records, operating conditions and code requirements before we can determine the best way forward.” 

Starting with the System 

For Shahzad, pipeline design begins with understanding the system. Required flow, operating and design pressures, pipe size and material, existing conditions, location and class requirements all shape the design. On existing pipelines, their historical records, previous testing, operating history and integrity information are also important. 

“As flow increases, the pressure drop through the pipeline also increases,” he explains. “We then need to see whether the existing pipeline and stations can handle that demand or whether something needs to change.” 

Depending on the system, that could mean increasing pipe size, uprating an existing pipeline where justified, upgrading a station, or changing pressure regulation. 

“Usually there are a few possible solutions,” Shahzad says. “so we look at the overall system and decide which option makes the most sense technically and practically.” 

Beyond the Design 

Shahzad’s experience across engineering, construction, testing and commissioning has also changed the way he approaches design. 

“I don’t just look at whether the design is technically correct,” he says. “I’m also thinking about the people who will eventually have to build, test and operate it.” 

For Shahzad, that means looking beyond whether the design works on paper. He considers whether there is enough room to make the welds, how the existing line will be isolated, whether a tie-in can actually be made as shown, and how the new piping will be tested and commissioned. 

“Something which looks simple on a drawing can be quite difficult in the field,” he says. “I try to catch those things during design wherever possible rather than leaving them for the construction team to sort out later.” 

The Challenge Below Ground 

That thinking was put to the test during FortisBC’s Coastal Transmission System and Lower Mainland Intermediate Pressure System Upgrade projects, where Shahzad worked with large-diameter transmission pressure and intermediate pressure pipelines in developed urban areas. 

The design had to account for hydraulic and future capacity requirements while also working around existing utilities, road space, crossings, traffic, construction access, tie-in locations, pipeline depth, and separation requirements. 

“In an urban environment, moving the pipeline alignment even slightly can solve one problem but create another one with an existing utility, crossing or road constraint,” Shahzad says. 

The team worked through each area, evaluating different routing and construction options, and looking for the best balance between engineering requirements and what could realistically be built. 

“There wasn’t one single issue that made the project difficult,” he says. “It was the number of different constraints that all had to be considered together.” For Shahzad, that is what pipeline engineering really comes down to. 

For Shahzad, that is what pipeline engineering really comes down to. 

“The calculations and code requirements are obviously important, but you also need to understand the field conditions and how the design is actually going to be built and operated.”