Project Description
The Surrey–Langley SkyTrain (SLS) Extension project is a major rapid transit infrastructure initiative that will expand the SkyTrain network into the Fraser Valley. This portion of the work covers independent Quality Assurance (QA) oversight of precast concrete walkway support units, and trap girders fabricated by Con-Force Structures for the elevated guideway system.
RAM ensures all fabrication, testing, and documentation activities meet contrast specification, engineering design requirements, and Canadian Standards Association (CSA) standards. The QA scope includes verification of Quality Control (QC) records, audit of non-conformance and corrective action reports, and validation of all pre-pour and post-pour inspection documentation prior to shipment.
Our Role
As Owner’s Representative, RAM’s role includes:
The Pre-Pour Phase
- Reviewing of documents such as Issued for Construction (IFC) drawings, mix design approvals, and material certificates;
- Inspection of formwork and verification of reinforcement layout, spacing, cleanliness, and cover in accordance with CSA A23.4 and IFC tolerances.
The Pour Phase
- Verifying concrete placement, temperature, and batch time compliance;
- Witnessing and recording field tests for slump/slump flow, air content, and temperature;
- Monitoring consolidation and vibration to prevent segregation or displacement of rebar and embedded items.
The Post-Pour Phase
- Dimensional checks within CSA and design tolerances, and surface finish elevation to confirm Class 2 uniformity;
- Reviewing of curing data to confirm compliance and verification of identification markings;
- Reviewing and close-out of Non-Conformance Reports (NCR), ensuring approved corrective actions are implemented;
- Ensuring QA records are reviewed, signed off, and included in the quarterly fabrication status reports by the P.Eng.