Project Summary
Client
SNC Lavalin
Budget
$250 Million
Services
Construction Management
Market
Infrastructure, Transportation
Project Description
Coordinated construction and design for utility relocations, traffic detours, and temporary electrical works. Managed accommodation work to facilitate the excavation and construction of the cut and cover tunnel. Coordinated the construction of Yaletown station and the restoration Cambie Street following tunnel construction and backfill. Assisted in accelerating the project schedule by three months by successfully managing the installation of 12 temporary bridges and detours on urban arterial streets.