Project Summary

Client
FTG Constructors

Budget
$18.1 Million

Services
Construction Management

Market
Energy, Transportation

Project Description

The South Fraser Perimeter Road, Highway 17, project electrical works included the removals of existing streetlights and signals contained within the future road allowance, as well as the installation and activation of numerous new signals, streetlights, and Intelligent Transportation System (ITS) conduit to be utilized in the future.

RAM’s Role

RAM was retained by the joint venture, FTG Constructors, to engage in design review, scheduling & coordinating, contract administration, and services design and planning. RAM worked with BC Hydro to fast track the application and connection of the electrical services.

Project Highlights

The $18.1 million scope included the installation of:

  • 38 km of ITS conduit
  • 7 Signalized traffic intersections
  • Streetlights for interchanges and intersections
  • 40 permanent electrical services
  • 5 temporary traffic signals (with detour programming) and streetlights