Project Summary
Client
ePac Flexible Packaging
Budget
$290,000
Services
Electrical Engineering
Market
Utility
Project Description
This project, completed in 2020, consisted of engineering and designing a new pad-mounted outdoor unit sub, coordination with BC Hydro, and construction support.
Our Role
RAM coordinated with BC Hydro for several services, including the following:
- Preparing civil design at new service location.
- Identifying the proposed unit sub location.
- Preparing site layout drawings for BC Hydro,
- Designing and engineering the unit substation layout as per Canadian Electrical Code and BC Hydro Primary Guide.
- Completing fuse coordination engineering as per BC Hydro Primary Guide.
- Engaging structural engineering firm for unit substation concrete pad design.
- Issuing a compilation of the construction package for contractors.
- Conducting Engineer of Record field review of unit substation during construction.
- Completing record drawings for unit substation.
- Coordinating with BC Hydro to energize unit substation.