Project Description

This project, completed in 2020, consisted of engineering and designing a new pad-mounted outdoor unit sub, coordination with BC Hydro, and construction support.

Our Role

RAM coordinated with BC Hydro for several services, including the following:

  • Preparing civil design at new service location.
  • Identifying the proposed unit sub location.
  • Preparing site layout drawings for BC Hydro,
  • Designing and engineering the unit substation layout as per Canadian Electrical Code and BC Hydro Primary Guide.
  • Completing fuse coordination engineering as per BC Hydro Primary Guide.
  • Engaging structural engineering firm for unit substation concrete pad design.
  • Issuing a compilation of the construction package for contractors.
  • Conducting Engineer of Record field review of unit substation during construction.
  • Completing record drawings for unit substation.
  • Coordinating with BC Hydro to energize unit substation.