Project Summary

Client
FTG Constructors

Budget
$0.9 Million

Services
Construction Management

Market
Utility

Project Description

This project consisted of relocating a 65LM steel section (895mm dia.) of a Metro Vancouver trunk water main. The relocation was required to avoid a planned bridge abutment and minimize the structural span. This put the worksite in close proximity to the red-coded Norum Creek stream. As part of the relocation works, a cast in place valve chamber was completed with a new butterfly valve. The steep terrain required temporary shoring including sheet piles and soil anchors.

RAM’s Role

RAM was retained by the joint venture, FTG Constructors, to engage in preliminary design review with Metro Vancouver, and to manage the schedule, procurement, and construction phases, and to ensure the works remained on budget. RAM worked closely with the designers to create a design that allowed minimal shutdown duration of the watermain.

Project Highlights

  • Limited workspace on steep terrain
  • Double bends tie-in with welded steel pipes
  • Hydro-static testing in a sensitive environment